DEEZA
CHASSIS PARTS BREAKS GROUND FOR NEW PRODUCTION PLANT
280,000
sq. ft. facility will nearly double company's capacity; slated
for Fall 2012 completion
As a
technology focused manufacturer of premium chassis parts for the
global aftermarket, we have broken ground on a new 280,000 sq.
ft. production plant in Turkey. At an estimated cost of $8
million, the new facility is scheduled for completion in the
fall of 2012 and will nearly double our current production
capacity.
Over the last
several years, we see a major increase in demand for our premium
quality chassis parts in both Europe and USA. As a result, our
current production plant is very close to being fully utilized.
Until the new plant goes into production, we will use expanded
labor and work hours to compensate for this. With its enhanced
capabilities, our new facility will position us for future
market and competitive challenges.
Deeza Chassis
Parts in the USA and its parent company Disa Automotive Ltd. in
Turkey will continue to make future investments, as they have
during the last 20 years, to facilitate the production of
quality chassis parts.
Gokhan Kuru, Ph.D.
President
Deeza Chassis Parts
Please click the icons below for more photos and progress.
Floors & Sidings 16-Dec-2011
Office Building &
Floors 08-Sept-2011
Roof 12-Aug-2011
Main
Beams Construction Completed 27-July-2011
Main
Beams Construction 7-July-2011
Foundation
Work, Stage 3 24-June-2011
Foundation
Work, Stage 2 09-June-2011
Foundation
Work, Stage 1 03-June-2011
Excavation
Completed 28-May-2011
Excavation
Started 13-May-2011
Design & Plans
13-May-2010 |